Which of the following is a ground for an interim payment?

Explanation:
Interim payments are provisional damages ordered before trial to prevent financial hardship when liability is clear or highly likely. They can be granted when liability is admitted, or there is a judgment in favor of the claimant, or the court is likely to award a substantial amount if the case were tried. This reflects the purpose of interim relief: to ensure the claimant is not left waiting for a full trial to receive funds for damages. So the best ground is that liability is admitted or there is a judgment, or the expected trial award would be substantial. Interim payments before trial are possible, they do not require a separate contract, and a dispute over liability does not automatically force dismissal; the court can still consider interim relief in appropriate circumstances.

Interim payments are provisional damages ordered before trial to prevent financial hardship when liability is clear or highly likely. They can be granted when liability is admitted, or there is a judgment in favor of the claimant, or the court is likely to award a substantial amount if the case were tried. This reflects the purpose of interim relief: to ensure the claimant is not left waiting for a full trial to receive funds for damages.

So the best ground is that liability is admitted or there is a judgment, or the expected trial award would be substantial. Interim payments before trial are possible, they do not require a separate contract, and a dispute over liability does not automatically force dismissal; the court can still consider interim relief in appropriate circumstances.